Skip to content
Published 2026-02-18 · 8 min read

Summer Construction Season: Planning Your Ceiling Project Timeline

May through September is peak construction season in Northern California. Everybody wants their project done before fall. Here's how to plan a ceiling project so it actually finishes on time.

Every year we see the same pattern. Projects that could have been on our schedule in March show up in June asking to start in July. By then, material lead times are extended, our crews are committed, and the project ends up pushing into October.

It doesn't have to go that way. Here's the timeline reality for commercial ceiling projects during summer construction season, and what you can do to stay ahead.

Why Summer Is So Busy

Three things converge in summer:

  • School projects: K-12 and university work happens during summer break. Every school district in the Sacramento region wants their ceiling work done between June and August. That's a massive share of our industry's capacity.
  • Budget cycles: Many facility budgets reset July 1. Deferred maintenance projects get greenlit and want to start immediately.
  • Weather-dependent projects: Ground-up construction accelerates in dry months. Interior finishes (including ceilings) stack up in the schedule behind framing, MEP, and drywall.

Material Lead Times in Peak Season

Standard acoustical ceiling tiles (Armstrong Cortega, USG Radar, CertainTeed BET-197) are usually in stock. Grid components — the same. These products ship from regional distribution centers within a few days.

Specialty products are different:

  • Wood ceilings (9Wood, Rulon): 6–12 weeks from order. Custom species or finishes push to 14+ weeks. See our wood ceiling guide for details.
  • Metal ceilings: 4–8 weeks. Custom perforations or finishes add time.
  • Premium tiles (Armstrong Ultima, CertainTeed Symphony): Usually stocked, but specific edge details or sizes can be back-ordered during peak.
  • Specialty baffles and clouds: 3–6 weeks. Custom shapes longer. See our baffle guide.

The mistake is waiting until the GC says "we're ready for ceilings" to order materials. By then you've added weeks to the schedule that didn't need to be there.

The Smart Timeline: Work Backwards

If your ceiling needs to be done by August 15, here's the timeline working backward:

  • August 10–15: Tile placement, punch list, inspection
  • August 1–10: Grid installation, above-ceiling coordination
  • July 25–31: Wall angle installation (ceiling contractor mobilizes)
  • July 1–24: Other trades complete above-ceiling rough-in (HVAC, electrical, plumbing, fire sprinkler)
  • June 15: Materials on site (or at least confirmed and shipped)
  • May 15: Material ordered, submittals approved
  • April 15: Ceiling contractor awarded, submittals submitted
  • March: Project out to bid, ceiling scope defined

That's a 5-month runway for a standard project. Wood or metal ceilings need 6–7 months. If your target completion is August and you're starting to plan in June, you're already behind.

What Causes Delays (And How to Avoid Them)

Submittal Ping-Pong

The spec says Armstrong Ultima. The contractor bids CertainTeed Symphony as a substitution. The architect reviews, asks questions, requests a sample. Two weeks gone. Then a revision. Another week. Get submittals moving early and respond fast. Read our GC guide to ceiling specs for more on this process.

Above-Ceiling Trades Not Done

We can't install ceiling grid with HVAC duct still going in above it. And we definitely can't place tiles until above-ceiling inspection passes. If the electrician is running conduit the same week we're hanging grid, everybody's slow. Coordinate the schedule so mechanical, electrical, and plumbing trades are substantially complete before the ceiling contractor mobilizes.

Site Conditions

Ceiling tiles need a weather-tight building with HVAC running. Mineral fiber tiles absorb moisture and sag. If the building isn't enclosed or the HVAC isn't commissioned, tiles can't go in. This is especially common on summer ground-up projects where the building envelope closes late.

Tips for GCs and Facility Managers

  • Bid early: Get ceiling bids 4–6 months before you need the work done
  • Order materials early: Even if you can't start yet, ordering locks in pricing and availability
  • Pre-approve substitutions: If the spec product has long lead time, get alternates approved before they're needed
  • Schedule ceiling early in the finish sequence: Grid goes up before some finishes, tiles drop in last
  • Communicate: Let your ceiling sub know about schedule changes as they happen, not the week before mobilization

Need a Summer Project Planned?

Elite Acoustics Inc handles commercial ceiling projects across Sacramento and Northern California. The earlier you engage us, the smoother the project goes. Contact us for a quote or read about how we work.

Related Reading